This post is later than usual as I went away with the boys to Port Augusta to do some train spotting and ride the Afghan Express and ran out of time. During August it has again seen a very significant proportion of my time being taken up with family matters but some hobby time was found and I managed to work on: Control Panels, Maintenance, Ops Sessions, WiFi Fast Clock and Stronger Magnets Under Loads.
Control Panels
The new local panels for Jimtown and Adamsville have been installed with help from Don and Rosslyn.
Adamsville
Jimtown
Centennial Mills had to be removed to provide working room |
Maintenance Sessions
Following the ops session on 6th we had a debrief over afternoon tea and a number of issues were identified for improvement so I asked a few over for a few hours to help implement them.
Flintston Warehouse
The MDF used for the platforms at the warehouse had swelled slightly over winter and at the last ops session a number of the older blue box 50 foot boxcars were scraping the sides.... Rosslyn to the rescue using a rasp, file and vacuum cleaner and hey presto all good!
Uncoupling ramp for Coaling Tower
Instead of a big reach with an uncoupling device of some type it was suggested that an uncoupling ramp be installed to make life easier. Don had the longest arms so he was tasked to remove some ballast and fit the ramp.
Uncoupling Ramp Removal
Some issues had been identified while shunting at Jimtown when the consist was on the grade on the main - occasionally wagons uncoupled themselves and started rolling away. This was due to the uncoupling ramp so Rosslyn removed it for me and reinstated the ballast.
Putting Scenery Back
For the last couple of months there has been dialogue about the troublesome track that ended up being ripped out along with the surrounding scenery. Following the successful use of the new track in the ops session on the 6th it was time to start the reinstatement. Chris took the lead as he has been doing a great job on his layout.
Cold days here so heater deployed to assist drying |
Ballasting
Rosslyn continued with ballasting the double track main at Fleets Loop up to and including Helix Junction.
Inkjet Printing Failure
I should have know better than to get wet water and glue anywhere near inkjet printed rock wall - forgot about the massive fail a few years back....
Just another thing to be attended to...
Ops Session Monday 6th
Despite loosing two operators at the last minute 8 of us had a good session with only a few glitches along the way. Barry, Chris, Des, Don, John, Rosslyn, Wayne and I ran a total of 43 movements during the three hour session. The session proved we need two operators in the main yard and one operator was "maxed out" and it showed.
Movements by Operator
Movements by Time
Ops Session Monday 20th
Movements by Operator
Movements by Time
Here is a link to the train graph with 57 movements if you are interested.
Well after a couple of last minute operator losses Alex, Barry, Chris, Don, Peter J, Rosslyn, Wayne and I had some fun however some gremlins were at work and after some power issues everything died..... We were about three quarters of the way through the session. Investigations as to what has failed will have to wait for a while as there is quite a few family things going on up to the end of the month.
It would appear the amount of work in Hornertown is beyond most operators so more though and feedback will be sought on how to address this.
A short video based on Alex's photographic work...
WiFi Fast Clock Master
I have finally gotten around to the final assembly and installation of all the modules.
Testing the Master at the table |
Testing the Slaves (I could only power three at a time) |
Row 8 of 32 died on one display |
Huntington Slave |
Master Near Jimtown |
Above Hornertown Sunset - Shasta Slave |
Above Flintston - Iron Hill - Stanvac Slave |
Between Jimtown - Onka Valley Slave |
Stronger Magnets Under Loads
The existing magnets have always been a bit weak so I decided I needed to add stronger ones to make load remove easier. I found some on Ebay which were 9 mm x 3 mm N50 Disc Round Neodymium.
Positioning alongside the existing magnets was a challenge until I realised I could put one on top of the load against the existing magnet then add the new one and position it then add supper glue.
I am hoping the new stronger magnets will be more reliable during operating session 39 cars have them to date.
Ops Session at Wayne's
I attended two ops sessions at Wayne's this month and enjoyed both of them. The second one was in Wayne's words "The slackest session...." Well the slower pace was appreciated by all that attended. The general consensus was a"A great session"....
In conclusion
Lots of good but some bad this month.
I am hoping the family issues come to a conclusion at the end of this month and a new leaf appears. I will work on the issues that caused the last op session to end early .
On a high note some of our group weent to the "Cross Roads of Australia - Pt Augusta" to do some train spotting and ride the Afghan Express from Pt Augusta to Quorn and return. Were away for 6 days - 5 nights and we were in the territory of the 12" to the foot guys who work in the Pt Augusta Loco Workshops.
I will try post the train spotting stuff soon.
Till the end of September.....
-ooOOOoo-
No comments:
Post a Comment